Engineering, Procurement & Construction
Unit | Client / Location | Work Scope | Duration |
---|---|---|---|
1 |
Larsen & Toubro Limited Deen Dayal West Field Development |
Construction for N14 jackect & N17, piles and conductor – ONGC (Mumbai high field) 2545 mt Tonnage 2,545 ton & 2,770mt |
May 2010 – Jan 2011 |
2 |
Larsen & Toubro Limited/GSPC Deen Dayal West Field Development |
Fabrication, loadout and seafastening of 6 legged jacket. Tonnage 4,530 |
Apr 2010 – Jan 2011 |
3 |
Newfield Peninsular Malaysia Inc. PM329 East Piatu Development Project |
Provision of fabrication, procurement, commissioning, loadout and seafastening of topside, CPP, living quarter and bridge of East Piatu development. Tonnage 4,161 mt |
Jul 2010 – Aug 2011 |
4 |
Murphy Sarawak PC of WP-PA Topside |
Fabrication and erection of coller deck structure, piping work, equipment function test, load-out and sea-fastening. Tonnage 590 mt |
Jun 2002 – Oct 2002 |
5 |
Newfield Malaysia PC of West Belumut WHP – Jacket & Topside |
Provision of procurement, construction of jacket and topside. Tonnage 1.153 mt |
May 2009 – Feb 2010 |
6 |
Petrofac Malaysia EPC Berantai Field Development Project – Topside & Jacket |
EPCC of wellhead platform (WHP-I) and the Angsi field tie-in at the Andre-A platform for Berantai field development project, block PM309. Tonnage 1,400 mt & 1,600 mt |
Dec 2010 – Sep 2011 |
7 |
Petrofac Malaysia SEPA-EPC of Process Skids & Refurbishment of MOPU |
EPCIC subcontract for mobile offshore production unit (MOPU) and wellhead support structure (WHSS) for Sepat early production system (EPS) for PCSB. Tonnage 1,200 mt |
Mar 2011 – Sep 2011 |
8 |
Murphy Malaysia FEPCIC – Wellhead Platform for Patricia |
Engineering, procurement, construction and commissioning (EPCC) of Patricia satellite. Tonnage 1,285 mt |
Aug 2011 – Mar 2011 |
9 |
Afcons – Gunanusa Joint Venture / ONGC (India) ICP-R and ICP-F3 Jackets |
Construction & onshore precomm of ICP-R, ICP-F3 jackets and piles. Tonnage 6,004 mt |
Aug 2009 – Dec 2010 |
10 |
Kebabangan Petroleum Operating Company Sdn Bhd (KPOC) KBB Substructure for Kebabangan Northern Hub Development |
Engineering, procurement, fabrication, inspection, testing and pre-commissioning, loadout & seafastening of KBB substructure, 8-legged jacket. Tonnage 13,393 mt |
Apr 2011 – Sep 2012 |
11 |
Petronas Carigali Sdn Bhd Tangga Barat Cluster Development |
Procurement and construction of Tangga Barat cluster development project (TBDR-A). Tonnage 5,013 mt |
Mar 2008 – May 2009 |
12 |
Exxon Mobile Exploration and Production Malaysia Inc. PC-Fabrication of Tapis R Jacket |
Procurement, fabrication, testing, loadout & tie-down of Tapis R jacket, piles & appurtenance. Tonnage 5,475 mt |
Mar 2012 – Jul 2013 |
13 |
Brunei Shell Petroleum Company Sdn Bhd AMPA-9 Compression Module |
Engineering, procurement & construction of AMPA-9 compression module. Tonnage 1,400mt |
Dec 2011 – Jan 2013 |
14 |
PT Sempec Indonesia ONGC – Heera Redevelopment Project |
Fabrication of 4 nos. Wellhead platform of deck, jacket, pile & conductors Heera development project. Tonnage 13,056 mt |
May 2007 – Nov 2008 |
15 |
Murphy Sarawak Oil Co Ltd EPC of Patricia Satellite for SK309/311 Sarawak Development Project |
Engineering, procurement and construction (EPC) of Patricia satellite (PT-SA) substructure and Serendah wellhead platform (WHP) template for SK309/311 Sarawak development project field developemnt. Tonnage 4,500mt |
2012 – 2013 |
16 |
Kencana Mermaid Drilling Sdn Bhd Self Erected Tender Rig & Derrick Equipment Set (KM-I) |
Design, construction & completion of self erected tender rig and derrick equipment set. Tonnage 8750 mt |
2009 – 2010 |
17 |
Bechtel – Wheatstone LNG Plant – ISBL Modules Wheatstone Project LNG Plant – Module Fabrication ISBL |
PC – Wheatstone LNG plant – ISBL modules. Tonnage 65,909 ton |
2011 – present |
18 |
Cameron Limited / BHP Biliton (Australia) BHP Pyrenees |
Engineering, procurement and construction of subsea manifolds and foundation mud mats. Tonnage 810 mt |
2007 – 2009 |
19 |
Aker Kvaerner (M) Sdn Bhd / Reliance Inductries Limited Ltd (India) Reliance KG-D6 |
9 units : 3 manifolds, 6 suction anchors for manifolds, I DWPLEM with suction anchor, I UDH with suction anchor, 3 SDA with suction anchors. Tonnage 2,337 mt |
2006 – 2007 |
20 |
FMC Wellhead Equipment Sdn Bhd (Malaysia) Gumusut Kakap |
5 subsea Wellhead Equipment Sdn Bhd (Malaysia). Tonnage 600 mt |
2008 – 2009 |
21 |
Bumi Armada M20, Bumi Armada |
Engineering, procurement & construction |
2008 – 2009 |
22 |
Prosafe Production Services Pte Ltd Prosafe Azurite Development Module Construction |
Detail engineering for electrical module and work drawings for all other module, procurement, fabrication, assemble, erection T&C |
2007 – 2008 |